Which process involves developing a working replica of the system or some aspect of the system?

Show

MIS 573 Chapter 5 Quiz

Creating the WBS is a subprocess associated with which process in project scope management?

During which approach do team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS?

Mind mapping can be used for developing WBSs using which approach?

top-down or bottom-up approach

What is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed referred to as?

requirements traceability matrix

What is the main technique used in creating a WBS, which involves subdividing project deliverables into smaller pieces?

the tendency for project scope to keep getting bigger and bigger

What process involves formal acceptance of the completed project scope by the stakeholders?

Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?

Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them?

Which action involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?

Which approach for constructing a WBS involves refining the work into greater and greater levels of detail?

Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?

Which approach for constructing a WBS uses a similar project's WBS as a starting point?

Which document contains a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project?

Which document should list and describe all of the deliverables required for the project?

Which is recommended for the creation of a good WBS?

A unit of work should appear at only one place in the WBS

Which output documents how project needs will be analyzed, documented, and managed?

requirements management plan

Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?

Which process involves identifying and modeling business events, who initiated them, and how the system should respond to them?

Which process uses highly organized and intensive workshops to bring together project stakeholders�the sponsor, users, business analysts, programmers, and so on�to jointly define and design information systems?

Which statement best describes scope?

work involved in creating the products and the processes used to create them

Which task is at the lowest level of the WBS?

Which technique is used for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks?

mind mapping
Correct Answer:
Correcta. mind mapping
Q

Which term refers to the difference between planned and actual performance?

Which process involves developing a working replica of the system or some aspect of the system?

Kinh Nghiệm Hướng dẫn Which process involves developing a working replica of the system or some aspect of the system? Mới Nhất

Bùi Phạm Vân Anh đang tìm kiếm từ khóa Which process involves developing a working replica of the system or some aspect of the system? được Update vào lúc : 2022-08-24 03:50:06 . Với phương châm chia sẻ Bí kíp Hướng dẫn trong nội dung bài viết một cách Chi Tiết 2022. Nếu sau khi đọc tài liệu vẫn ko hiểu thì hoàn toàn có thể lại phản hồi ở cuối bài để Ad lý giải và hướng dẫn lại nha.

b. Scope planningc. Scope controld. Scope baselineAScope validation involves formal acceptance of the completed project deliverables. This acceptance isoften achieved by a customer inspection and then sign-off on key deliverables.22. _____ refers to the difference between planned and actual performance.a. Decompositionb. Variancec. Scope validationd. Scope creepBVariance is the difference between planned and actual performance

Nội dung chính

    Which approach for constructing a WBS involves refining the work into greater?Which approach for constructing a WBS starts with the largest?What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces quizlet?Is a WBS construction technique that uses branches radiating from a core idea to structure thoughts and ideas?What term is used in developing a working replica of the system or some aspect of the system to help define user requirements?Which action involves reviewing the project charter requirements documents and organizational process assets to create a scope statement adding Mor?Which approach for constructing a WBS uses a similar project WBS as a starting point?What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces Group of answer choices?

23. _____ refers to the process of developing a working replica of the system or some aspect of thesystem.

Get answer to your question and much more

24. _____ is a process for identifying and modeling business events, who initiated them, and how thesystem should respond to them.

Get answer to your question and much more

Upgrade to remove ads

Nội dung chính

    Which approach for constructing a WBS involves refining the work into greater?Which approach for constructing a WBS starts with the largest?What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces quizlet?Is a WBS construction technique that uses branches radiating from a core idea to structure thoughts and ideas?

Only SGD 41.99/year

    Flashcards

    Learn

    Test

    Match

    Flashcards

    Learn

    Test

    Match

Terms in this set (26)

Which process involves developing a working replica of the system or some aspect of the system?

a. Use case modeling
b. Prototyping
c. Decomposition
d. Variance

Prototyping

Which action involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?

a. Validating scope
b. Defining scope
c. Controlling scope
d. Creating scope

Defining scope

Which document contains a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project?

a. business case
b. project charter
c. project scope statement
d. work breakdown structure

work breakdown structure

Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them?

a. Collecting requirements
b. Validating scope
c. Defining scope
d. Controlling scope

Collecting requirements

Which approach for constructing a WBS involves refining the work into greater and greater levels of detail?

a. bottom-up
b. mind mapping
c. analogy
d. top-down

top-down

What is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed referred to as?

a. requirements traceability matrix
b. Gantt chart
c. entity-attribute-value model
d. state transition table

requirements traceability matrix

Which is recommended for the creation of a good WBS?

a. The work content of a WBS item is independent of the WBS items below it.

b. Any WBS item should be the responsibility of all the people working on it.

c. A unit of work should appear only one place in the WBS.

d. Each WBS item should be created assuming that the requirements are inflexible.

A unit of work should appear only one place in the WBS.

Which process involves identifying and modeling business events, who initiated them, and how the system should respond to them?

a. Use case modeling
b. Prototyping
c. RAD
d. JAD

Use case modeling

Which term describes a product produced as part of a project?

a. work package
b. variance
c. deliverable
d. scope

deliverable

Which technique is used for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks?

a. analogy
b. mind mapping
c. bottom-up
d. top-down

mind mapping

Which statement best describes scope?

a. tasks that are decomposed into smaller tasks in a work breakdown structure

b. each level of work that is outlined in a work breakdown structure

c. end product created as part of a project that is delivered to the client

d. work involved in creating the products and the processes used to create them

work involved in creating the products and the processes used to create them

What is the main technique used in creating a WBS, which involves subdividing project deliverables into smaller pieces?

a. decomposition
b. conglomeration
c. accumulation
d. catalyzation

decomposition

Creating the WBS is a subprocess associated with which process in project scope management?

a. closing
b. monitoring and controlling
c. executing
d. planning

planning

Which term refers to the difference between planned and actual performance?

a. Variance
b. Decomposition
c. Scope creep
d. Scope validation

Variance

Mind mapping can be used for developing WBSs using which approach?

a. top-down or bottom-up approach
b. any approach
c. analogy approach only
d. bottom-up or analogy approach

top-down or bottom-up approach

Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?

a. Validating scope
b. Controlling scope
c. Creating scope
d. Defining scope

Validating scope

Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?

a. benchmarking
b. decomposition
c. variance
d. prototyping

Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?

Which document should list and describe all of the deliverables required for the project?

a. WBS
b. project charter
c. Gantt chart
d. scope statement

scope statement

What process involves formal acceptance of the completed project scope by the stakeholders?

a. Scope baseline
b. Scope control
c. Scope validation
d. Scope planning

Scope validation

During which approach do team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS?

a. mind mapping
b. bottom-up
c. top-down
d. analogy

bottom-up

What is scope creep?

a. subdividing project deliverables into smaller pieces

b. a task the lowest level of the WBS

c. the approved project scope statement and its associated WBS.

d. the tendency for project scope to keep getting bigger and bigger

the tendency for project scope to keep getting bigger and bigger

Which process uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems?

a. JAD
b. Use case modeling
c. RAD
d. Prototyping

JAD

Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?

a. top-down
b. bottom-up
c. mind mapping
d. analogy

top-down

Which approach for constructing a WBS uses a similar project's WBS as a starting point?

a. top-down
b. analogy
c. bottom-up
d. mind-mapping

analogy

Which output documents how project needs will be analyzed, documented, and managed?

a. project scope statement
b. WBS
c. requirements management plan
d. requirements traceability matrix

requirements management plan

Which task is the lowest level of the WBS?

a. work package
b. objective
c. deliverable
d. variance

work package

Sets found in the same folderPM Quiz 1

55 terms

lsmr1

PM Quiz 2

58 terms

lsmr1

PM Quiz 4__MC only

56 terms

lsmr1

PM Quiz 3__MC only

57 terms

lsmr1

Other sets by this creatorPM Exam 2

154 terms

lsmr1

PM Quiz 9__MC only

35 terms

lsmr1

PM Quiz 8__MC only

40 terms

lsmr1

PM Quiz 7__MC only

40 terms

lsmr1

Which approach for constructing a WBS involves refining the work into greater?

Cards

Term Products that are accepted by project stakeholders are considered to be validated deliverables.

Definition TRUE

Term The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.

Definition analogy bottom-up top-down mind mapping

Project Management Final_2 Flashcardswww.flashcardmachine.com › project-managementfinal2null

Which approach for constructing a WBS starts with the largest?

Cards

Term Analogy approach

Definition Creating a WBS by using a similar project's WBS as a starting point.

Term Top-down approach

Definition Creating a WBS by starting with the largest items of the project and breaking them into subordinate items.

Ch 5 Project Scope Management Flashcardswww.flashcardmachine.com › ...null

What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces quizlet?

ANS: C The main tool or technique involved in creating a WBS is decomposition—that is, subdividing project deliverables into smaller pieces.

Is a WBS construction technique that uses branches radiating from a core idea to structure thoughts and ideas?

Mind mapping is a technique that uses branches radiating out from a core idea to structure thoughts and ideas.

What term is used in developing a working replica of the system or some aspect of the system to help define user requirements?

CardsTerm analogy approachDefinition creating a WBS by using a similar project's WBS as a starting pointTerm prototypingDefinition developing a working replica of the system or some aspect of the system to help define user requirementsTest #2 Flashcards - Flashcard Machinewww.flashcardmachine.com › test234null

Which action involves reviewing the project charter requirements documents and organizational process assets to create a scope statement adding Mor?

3. Defining scope involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

Which approach for constructing a WBS uses a similar project WBS as a starting point?

In the analogy approach, you use a similar project's WBS as a starting point.

What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces Group of answer choices?

ANS: C The main tool or technique involved in creating a WBS is decomposition—that is, subdividing project deliverables into smaller pieces. Tải thêm tài liệu liên quan đến nội dung bài viết Which process involves developing a working replica of the system or some aspect of the system?

Which process involves developing a working replica of the system or some aspect of the system?

Clip Which process involves developing a working replica of the system or some aspect of the system? ?

Bạn vừa tham khảo Post Với Một số hướng dẫn một cách rõ ràng hơn về Video Which process involves developing a working replica of the system or some aspect of the system? tiên tiến nhất

Bạn đang tìm một số trong những ShareLink Tải Which process involves developing a working replica of the system or some aspect of the system? miễn phí.

Hỏi đáp thắc mắc về Which process involves developing a working replica of the system or some aspect of the system?

Nếu sau khi đọc nội dung bài viết Which process involves developing a working replica of the system or some aspect of the system? vẫn chưa hiểu thì hoàn toàn có thể lại Comments ở cuối bài để Mình lý giải và hướng dẫn lại nha #process #involves #developing #working #replica #system #aspect #system - 2022-08-24 03:50:06 Which process involves developing a working replica of the system or some aspect of the system?

Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?

Most project managers consider the top-down approach of WBS construction to be conventional. To use the top-down approach, start with the largest items of the project and break them into their subordinate items. This process involves refining the work into greater and greater levels of detail.

Which approach for constructing a WBS involves refining the work into greater?

Cards
Term Products that are accepted by project stakeholders are considered to be validated deliverables.
Definition TRUE
Term The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.
Definition analogy bottom-up top-down mind mapping
Project Management Final_2 Flashcardswww.flashcardmachine.com › project-managementfinal2null

What is the approach for constructing WBS?

Top-down approach: Top-down approach states that you need to take the biggest task or module in the project and break it down. It requires more logic and structure, and generally, it is a preferred method for creating WBS.

Which part of a statement of work defines all the broad requirements for a project?

The main purpose of the WBS is to define all of the work required to complete a project. Information from the project charter provides a basis for further defining the project scope.