MIS 573 Chapter 5 Quiz
Creating the WBS is a subprocess associated with which process in project scope management?
During which approach do team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS?
Mind mapping can be used for developing WBSs using which approach?
top-down or bottom-up approach
What is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed referred to as?
requirements traceability matrix
What is the main technique used in creating a WBS, which involves subdividing project deliverables into smaller pieces?
the tendency for project scope to keep getting bigger and bigger
What process involves formal acceptance of the completed project scope by the stakeholders?
Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?
Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them?
Which action involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?
Which approach for constructing a WBS involves refining the work into greater and greater levels of detail?
Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?
Which approach for constructing a WBS uses a similar project's WBS as a starting point?
Which document contains a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project?
Which document should list and describe all of the deliverables required for the project?
Which is recommended for the creation of a good WBS?
A unit of work should appear at only one place in the WBS
Which output documents how project needs will be analyzed, documented, and managed?
requirements management plan
Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?
Which process involves identifying and modeling business events, who initiated them, and how the system should respond to them?
Which process uses highly organized and intensive workshops to bring together project stakeholders�the sponsor, users, business analysts, programmers, and so on�to jointly define and design information systems?
Which statement best describes scope?
work involved in creating the products and the processes used to create them
Which task is at the lowest level of the WBS?
Which technique is used for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks?
mind mapping
Correct Answer:
Correcta. mind mapping
Q
Which term refers to the difference between planned and actual performance?
Which process involves developing a working replica of the system or some aspect of the system?
Kinh Nghiệm Hướng dẫn Which process involves developing a working replica of the system or some aspect of the system? Mới Nhất
Bùi Phạm Vân Anh đang tìm kiếm từ khóa Which process involves developing a working replica of the system or some aspect of the system? được Update vào lúc : 2022-08-24 03:50:06 . Với phương châm chia sẻ Bí kíp Hướng dẫn trong nội dung bài viết một cách Chi Tiết 2022. Nếu sau khi đọc tài liệu vẫn ko hiểu thì hoàn toàn có thể lại phản hồi ở cuối bài để Ad lý giải và hướng dẫn lại nha.
b. Scope planningc. Scope controld. Scope baselineAScope validation involves formal acceptance of the completed project deliverables. This acceptance isoften achieved by a customer inspection and then sign-off on key deliverables.22. _____ refers to the difference between planned and actual performance.a. Decompositionb. Variancec. Scope validationd. Scope creepBVariance is the difference between planned and actual performance
Nội dung chính
- Which approach for constructing a WBS involves refining the work into greater?Which approach for constructing a WBS starts with the largest?What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces quizlet?Is a WBS construction technique that uses branches radiating from a core idea to structure thoughts and ideas?What term is used in developing a working replica of the system
or some aspect of the system to help define user requirements?Which action involves reviewing the project charter requirements documents and organizational process assets to create a scope statement adding Mor?Which approach for constructing a WBS uses a similar project WBS as a starting point?What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces Group of answer choices?
23. _____ refers to the process of developing a working replica of the system or some aspect of thesystem.
Get answer to your question and much more
24. _____ is a process for identifying and modeling business events, who initiated them, and how thesystem should respond to them.
Get answer to your question and much more
Upgrade to remove ads
Nội dung chính
- Which approach for constructing a WBS involves refining the work into greater?Which approach for constructing a WBS starts with the largest?What is the main
technique used in creating a WBS which involves subdividing project deliverables into smaller pieces quizlet?Is a WBS construction technique that uses branches radiating from a core idea to structure thoughts and ideas?
Only SGD 41.99/year
Flashcards
Learn
Test
Match
Flashcards
Learn
Test
Match
Terms in this set (26)
Which process involves developing a working replica of the system or some aspect of the system?
a. Use case modeling
b. Prototyping
c. Decomposition
d. Variance
Prototyping
Which action involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?
a. Validating scope
b. Defining scope
c. Controlling scope
d. Creating scope
Defining scope
Which document contains a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project?
a. business case
b. project charter
c. project scope statement
d. work breakdown structure
work breakdown structure
Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them?
a. Collecting requirements
b. Validating scope
c. Defining
scope
d. Controlling scope
Collecting requirements
Which approach for constructing a WBS involves refining the work into greater and greater levels of detail?
a. bottom-up
b. mind mapping
c. analogy
d. top-down
top-down
What is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed referred to as?
a. requirements traceability matrix
b. Gantt chart
c.
entity-attribute-value model
d. state transition table
requirements traceability matrix
Which is recommended for the creation of a good WBS?
a. The work content of a WBS item is independent of the WBS items below it.
b. Any WBS item should be the responsibility of all the people working on it.
c. A unit of work should appear only one place in the WBS.
d. Each WBS item should be created assuming that the requirements are inflexible.
A unit of work should appear only one place in the WBS.
Which process involves identifying and modeling business events, who initiated them, and how the system should respond to them?
a. Use case modeling
b. Prototyping
c. RAD
d. JAD
Use case modeling
Which term describes a product produced as part of a project?
a. work package
b. variance
c. deliverable
d. scope
deliverable
Which technique is used for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks?
a. analogy
b. mind mapping
c. bottom-up
d. top-down
mind mapping
Which statement best describes scope?
a. tasks that are decomposed into smaller tasks in a work breakdown structure
b. each level of work that is outlined in a work breakdown structure
c. end product created as part of a project that is delivered to the client
d. work involved in creating the products and the processes used to create them
work involved in creating the products and the processes used to create them
What is the main technique used in creating a WBS, which involves subdividing project deliverables into smaller pieces?
a. decomposition
b. conglomeration
c. accumulation
d. catalyzation
decomposition
Creating the WBS is a subprocess associated with which process in project scope management?
a. closing
b. monitoring and controlling
c. executing
d. planning
planning
Which term refers to the difference between planned and actual performance?
a. Variance
b. Decomposition
c. Scope creep
d. Scope validation
Variance
Mind mapping can be used for developing WBSs using which approach?
a. top-down or bottom-up approach
b. any approach
c. analogy approach only
d. bottom-up or analogy approach
top-down or bottom-up approach
Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?
a. Validating scope
b. Controlling scope
c. Creating scope
d. Defining scope
Validating scope
Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?
a. benchmarking
b. decomposition
c. variance
d. prototyping
Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization?
Which document should list and describe all of the deliverables required for the project?
a. WBS
b. project charter
c. Gantt chart
d.
scope statement
scope statement
What process involves formal acceptance of the completed project scope by the stakeholders?
a. Scope baseline
b. Scope control
c. Scope validation
d. Scope planning
Scope validation
During which approach do team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS?
a. mind
mapping
b. bottom-up
c. top-down
d. analogy
bottom-up
What is scope creep?
a. subdividing project deliverables into smaller pieces
b. a task the lowest level of the WBS
c. the approved project scope statement and its associated WBS.
d. the tendency for project scope to keep getting bigger and bigger
the tendency for project scope to keep getting bigger and bigger
Which process uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems?
a. JAD
b. Use case modeling
c. RAD
d. Prototyping
JAD
Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?
a. top-down
b. bottom-up
c. mind mapping
d. analogy
top-down
Which approach for constructing a WBS uses a similar project's WBS as a starting point?
a. top-down
b. analogy
c. bottom-up
d. mind-mapping
analogy
Which output documents how project needs will be analyzed, documented, and managed?
a. project scope statement
b. WBS
c. requirements management plan
d. requirements traceability matrix
requirements management plan
Which task is the lowest level of the WBS?
a. work package
b. objective
c. deliverable
d. variance
work package
Sets found in the same folderPM Quiz 1
55 terms
lsmr1
PM Quiz 2
58 terms
lsmr1
PM Quiz 4__MC only
56 terms
lsmr1
PM Quiz 3__MC only
57 terms
lsmr1
Other sets by this creatorPM Exam 2
154 terms
lsmr1
PM Quiz 9__MC only
35 terms
lsmr1
PM Quiz 8__MC only
40 terms
lsmr1
PM Quiz 7__MC only
40 terms
lsmr1
Which approach for constructing a WBS involves refining the work into greater?
Cards
Term Products that are accepted by project stakeholders are considered to be validated deliverables.
Definition TRUE
Term The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.
Definition analogy bottom-up top-down mind mapping
Project Management Final_2 Flashcardswww.flashcardmachine.com › project-managementfinal2null
Which approach for constructing a WBS starts with the largest?
Cards
Term Analogy approach
Definition Creating a WBS by using a similar project's WBS as a starting point.
Term Top-down approach
Definition Creating a WBS by starting with the largest items of the project and breaking them into subordinate items.
Ch 5 Project Scope Management Flashcardswww.flashcardmachine.com › ...null
What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces quizlet?
ANS: C The main tool or technique involved in creating a WBS is decomposition—that is, subdividing project deliverables into smaller pieces.
Is a WBS construction technique that uses branches radiating from a core idea to structure thoughts and ideas?
Mind mapping is a technique that uses branches radiating out from a core idea to structure thoughts and ideas.
What term is used in developing a working replica of the system or some aspect of the system to help define user requirements?
CardsTerm analogy approachDefinition creating a WBS by using a similar project's WBS as a starting pointTerm prototypingDefinition developing a working replica of the system or some aspect of the system to help define user requirementsTest #2 Flashcards - Flashcard Machinewww.flashcardmachine.com › test234null
Which action involves reviewing the project charter requirements documents and organizational process assets to create a scope statement adding Mor?
3. Defining scope involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.
Which approach for constructing a WBS uses a similar project WBS as a starting point?
In the analogy approach, you use a similar project's WBS as a starting point.
What is the main technique used in creating a WBS which involves subdividing project deliverables into smaller pieces Group of answer choices?
ANS: C The main tool or technique involved in creating a WBS is decomposition—that is, subdividing project deliverables into smaller pieces. Tải thêm tài liệu liên quan đến nội dung bài viết Which process involves developing a working replica of the system or some aspect of the system?
Clip Which process involves developing a working replica of the system or some aspect of the system? ?
Bạn vừa tham khảo Post Với Một số hướng dẫn một cách rõ ràng hơn về Video Which process involves developing a working replica of the system or some aspect of the system? tiên tiến nhất
Share Link Down Which process involves developing a working replica of the system or some aspect of the system? miễn phí
Bạn đang tìm một số trong những ShareLink Tải Which process involves developing a working replica of the system or some aspect of the system? miễn phí.
Hỏi đáp thắc mắc về Which process involves developing a working replica of the system or some aspect of the system?
Nếu sau khi đọc nội dung bài viết Which process involves developing a working replica of the system or some aspect of the system? vẫn chưa hiểu thì hoàn toàn có thể lại Comments ở cuối bài để Mình lý giải và hướng dẫn lại nha #process #involves #developing #working #replica #system #aspect #system - 2022-08-24 03:50:06 Which process involves developing a working replica of the system or some aspect of the system?
Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?
Which approach for constructing a WBS involves refining the work into greater?
Term Products that are accepted by project stakeholders are considered to be validated deliverables. | Definition TRUE |
Term The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail. | Definition analogy bottom-up top-down mind mapping |